Enbridge Pipelines (NW) Inc. - S17P-005
Status:
Closed
Authorization:
Land Use Permit
Activity:
Pipeline
Start:
February 7, 2018
Expiry:
February 6, 2020
Staff:
AlecSandra Macdonald
Enbridge Pipelines (NW) Inc. is proposing to conduct Line 21 pipeline maintenance digs within the Saline River (KP 180.168 and KP 180.280). All excavation activities will be contained within Enbridge's existing right-of-way (MV2013P0011) however additional off-right-of-way land is required for temporary work space to accommodate vehicle and equipment staging, temporary material storage and excavation isolation activities. The Project will involve a watercourse crossing and there is the potential for a channel diversion. The associated application for a Type B Water Licence is S17L1-004.
- All Issuances (4)
- Annual Reports (7)
- Application and Related Docs (21)
- Assorted Management Plans (1)
- Consultations - Reviews - Work Plans (3)
- External Authorizations (1)
- Final Closure and Reclamation Plan (4)
- Final Plan and Clearance (4)
- Further Study Requested Sec. 22.2.b (1)
- Inspection Reports (5)
- Preliminary Screening (1)
- Shapefiles (1)
- Spill - Contingency - Emergency Response (3)
- Waste Management Plan (2)
Documents
Displaying 1 - 58 of 58
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 - Board Review of Enbridge Temporary Camp for 2019 - Feb 4_19.pdf (40.78 KB) | February 4, 2019 | February 8, 2019 |
S17P-005 - Enbridge Pipelines Inc. - Issuance Letter_Feb.7_18.pdf (335.37 KB) | February 7, 2018 | February 8, 2018 |
S17P-005 - Enbridge Pipelines Inc. - Land Use Permit_Feb.7_18-2.pdf (418.74 KB) | February 7, 2018 | February 8, 2018 |
S17P-005 - Enbridge Pipelines Inc. - Reasons for Decision_Feb.7_18.pdf (397.63 KB) | February 7, 2018 | February 8, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 - Enbridge - Lands permission granted for camp set-up - Jan 30-_18.pdf (81.24 KB) | January 30, 2018 | January 30, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 - Enbridge Final Plan Staff Report - Dec 7_22.pdf (262.34 KB) | December 7, 2022 | December 7, 2022 |
S17P-005 – Enbridge - Letter of Clearance – Dec 7_22.pdf (218.82 KB) | December 7, 2022 | December 7, 2022 |
S17P-005 - Final Plan - Maps - Oct 7_21.pdf (2.89 MB) | October 7, 2021 | October 28, 2021 |
S17P-005 - Saline Creek - Final Plan - Request for Clearance - Oct 7_21.pdf (91.77 KB) | October 7, 2021 | October 28, 2021 |
2. Initial/Renewal Application
Document | Received/Sent | Uploaded |
---|---|---|
S17L1-004 S17P-005 - Enbridge - Staff Report 1 - Feb 7_18.pdf (815.92 KB) | February 7, 2018 | February 7, 2018 |
S17L1-004 S17P-005 - Enbridge - Line 21 Integrity Dig Saline River - Review Summary Table with Attachments - Jan 27_18.pdf (1.35 MB) | January 27, 2018 | January 27, 2018 |
S17L1-004 S17P-005 - Enbridge Responses to Review Comments and Draft Conditions with Attachments - Jan 25_18.pdf (405.45 KB) | January 25, 2018 | January 25, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17L1-004 S17P-005 - Enbridge - Board Decision WL and LUP Application - Further Study Required - Jan 29_18.pdf (96.56 KB) | January 29, 2018 | January 30, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Preliminary Screening - Feb 7_18.pdf (338.01 KB) | February 7, 2018 | February 7, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Revised Appendix IV - Spill Contingency Plan - Dec 14_17.pdf (2.32 MB) | December 14, 2017 | December 15, 2017 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Revised Appendix III - Waste Management Plan - Dec 14_17.pdf (1.51 MB) | December 14, 2017 | December 15, 2017 |
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 - 2020 Annual Report - Mar 18_21.pdf (657.27 KB) | March 18, 2021 | March 31, 2021 |
S17P-005 - Cover Letter - 2020 Annual Reports - Mar 31_21.pdf (21.66 KB) | March 31, 2021 | March 31, 2021 |
S17P-005 S17L1-004 - 2020 Annual Report - Mar 18_21.pdf (631.23 KB) | March 31, 2021 | March 31, 2021 |
S17P-005 - Enbridge Pipelines - 2019 Annual Land Use Permit Report - Mar_18_20.pdf (1.81 MB) | March 18, 2020 | March 18, 2020 |
S17L1-004 - Enbridge Pipelines Inc. - 2019 Annual Report Cover Letter - Mar_17_20.pdf (21.76 KB) | March 17, 2020 | March 17, 2020 |
S17P-005 - S17L1-004 - Review Comment Table with Letter from GNWT-ENR - Review of 2018 Annual Reports - May 7 _19.pdf (225.87 KB) | May 7, 2019 | May 7, 2019 |
S17P-005 - Line 21 Annual Land Use Permit Report - Mar 29_19.pdf (9.94 MB) | March 29, 2019 | April 1, 2019 |
Document | Received/Sent | Uploaded |
---|---|---|
Enbridge - Inspector Recommendation - File Closure - Correspondence - Aug8_22.pdf (638.71 KB) | August 8, 2022 | October 26, 2022 |
S17P-005 - Inspection Report - June-27-2022.pdf (1.13 MB) | August 8, 2022 | October 19, 2022 |
S17P-005 - Inspection Report July-9-19 - Jul 15_19.pdf (1.01 MB) | July 15, 2019 | July 15, 2019 |
S17P-005 - Inspection Report - Mar 18_19.pdf (345.98 KB) | March 18, 2019 | March 21, 2019 |
S17P-005 - GNWT-Lands Inspection Report for Feb 26 2018 - Mar 22_18.pdf (562.13 KB) | March 22, 2018 | March 23, 2018 |
6. Management Plans
Document | Received/Sent | Uploaded |
---|---|---|
S17L1-004 S17P-005 - Revised WMP and SECP - Staff Conformity Confirmation - Feb 16_18.pdf (334.61 KB) | February 16, 2018 | February 16, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Enbridge - Spill Contingency Plan - Version 1.1 - Feb 16_18.pdf (12.6 MB) | February 16, 2018 | February 19, 2018 |
S17P-005 S17L1-004 - Staff Confirmation of Conformity - Spill Contingency Plan - Feb 19_18.pdf (283.9 KB) | February 19, 2018 | February 19, 2018 |
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Enbridge - Revised Waste Management Plan - Version 1.1 - Feb 15_18.pdf (3.35 MB) | February 15, 2018 | February 16, 2018 |
8. Closure and Reclamation
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Enbridge - CRP V1 - Review Summary Table - Mar 26_18.pdf (378.97 KB) | March 26, 2018 | March 27, 2018 |
S17L1-004 S17P-005 - Staff Report - CRP V1 - Mar 26_18.pdf (486.94 KB) | March 26, 2018 | March 27, 2018 |
S17L1-004 S17P-005 - Enbridge - Closure and Reclamation Plan - Version 1.0 - Feb 28_18.pdf (1.89 MB) | February 28, 2018 | March 27, 2018 |
S17L1-004 S17P-005 - Board approval - CRP V1- Mar 26_18.pdf (312.49 KB) | March 26, 2018 | March 27, 2018 |
9. GIS Data
Document | Received/Sent | Uploaded |
---|---|---|
S17P-005 S17L1-004 - Saline River Shapefiles - Dec 4_17.zip (42.15 KB) | December 4, 2017 | December 15, 2017 |