Closure and Reclamation Consolidation Project, Colville Lake Area

The Water Licence S19L1-003 (anticipated; application currently under review) and the Permit S19A-004 (anticipated; application currently under review) related to the same is the consolidation of four sets of expired licences and permits listed below. 

The expired permits and licences to be consolidated for the closure and reclamation operations are:

 

  • S01A-007 (Permit) and S01L1-003 (Licence): Oil and Gas exploration drilling project located at the south of Lac Belot and Tweed Lake, near Colville Lake, NT; involving well sites C-49, and M-17 and remote sump P-27. The project is currently at the monitoring/reclamation stage.  
  • S03A-007 (Permit) and S03L1-015 (Licence): Oil and Gas exploration drilling project located at the Lac Maunoir area, approximately 35km north-east of Colville Lake; involving well sites C-34 and L-80. The project is currently at the monitoring/reclamation stage.  
  • S03A-008 (Permit) and S03L1-016 (Licence): Oil and Gas exploration drilling project located at the Tunago-Nogha area, approximately 73km south of Colville Lake, NT (and north of Tunago Lake); involving well sites K-14, B-23 and E-44. The project is currently at the monitoring/reclamation stage.  
  • S04A-010 (Permit) and S04L1-011 (Licence): Oil and Gas exploration drilling project located at the Lac Maunoir area approximately 65km north-east of Colville Lake; involving well sites E-35 and A-67. The project is currently at the monitoring/reclamation stage.  

 

These permits and licences were originally held by Paramount Resources Ltd. and Apache Canada Ltd. and were later Assigned to MGM Energy. The Land Use Permit (S19A-004) and accompanying Water Licence (S19L1-003) are being sought so that MGM can proceed with the final closure and reclamation of the Nogha and Maunoir area well sites, as listed above. MGM envisions the winter road/lease construction and abandonment operations no later than the winter 2022-2023 season. The scope includes activities winter road construction, abandonment operations, reclamation, remediation, camps, helicopter access and monitoring. MGM has requested the Licence (and related Permit) to be valid for five years.




Documents

Displaying 1 - 21 of 21
E.g., 08/14/2020
E.g., 08/14/2020

1. Permit - Licence - Other Issuances

Security and Water Use Fees
Document Received/Sent Uploaded
S19L1-003 - Water Licence Application Fee - May 21_20.pdf (19.84 KB) June 15, 2020 June 15, 2020
S19L1-003 - Water Use Fee - Nov_14_19.pdf (29.93 KB) November 5, 2019 November 5, 2019

2. Initial/Renewal Application

Application and Related Docs
Document Received/Sent Uploaded
S19L1-003 - Water Licence Application Fee - Jun 10_20.pdf (19.84 KB) June 18, 2020 June 18, 2020
S19L1-003 - Project Description - Attachment A - Nov_5_19.pdf (866.47 KB) November 5, 2019 November 5, 2019
S19L1-003 - Cover Letter for LUP and WL Consolidation - Nov_5_19.pdf (62.41 KB) November 5, 2019 November 5, 2019
S19L1-003 - Water Licence Application - Nov_5_19.pdf (254.87 KB) November 5, 2019 November 5, 2019
S19L1-003 - WL Application Maps - Lakes and Roads - Nov_5_19.pdf (10.07 MB) November 5, 2019 November 5, 2019
Consultations - Reviews - Work Plans
Document Received/Sent Uploaded
S19L1-003 - MGM Eneregy - Draft Licence conditions - Jul 30_20.pdf (1.08 MB) July 30, 2020 July 30, 2020
S19A-004 - S19L1-003 - Staff Report 1 - Invoking 22 (2) (b) - Jun 18_ 20.pdf (299.39 KB) June 18, 2020 June 19, 2020
S19L1-003 - Updated WL Security Estimate - May_22_20.pdf (29.21 KB) May 22, 2020 May 22, 2020
S19A-004 - S19L1-003 - E-mail Communication - Application Incomplete - May 7_20.pdf (321.37 KB) May 7, 2020 May 7, 2020
S19A-004 - S19L1-003 - MGM Response - Additional Information for LUP and WL Application - Apr 24_20.pdf (391.91 KB) April 24, 2020 April 24, 2020
S19L1-003 - Additional Information Request - Mar_26_20.pdf (190.12 KB) March 26, 2020 March 26, 2020
S19L1-003 - Additional Information Extension Request - Feb_11_20.pdf (261.18 KB) February 14, 2020 February 14, 2020
S19L1-003 - Application Incomplete - Nov 14_19.pdf (173.69 KB) November 14, 2019 November 14, 2019

6. Management Plans

Engagement Plan
Document Received/Sent Uploaded
S19L1-003 - Engagement Letter - Nov_5_19.pdf (60.04 KB) November 5, 2019 November 5, 2019
S19L1-003 - Engagement Plan and Record - Nov_5_19.pdf (1.58 MB) November 5, 2019 November 5, 2019
S19L1-003 - Engagement Presentation - Nov_5_19.pdf (7.79 MB) November 5, 2019 November 5, 2019
Spill - Contingency - Emergency Response
Document Received/Sent Uploaded
S19L1-003 - Spill Contingency Plan - Nov_5_19.pdf (9.92 MB) November 5, 2019 November 5, 2019
Waste Management Plan
Document Received/Sent Uploaded
S19L1-003 - EPP and WMP - Nov_5_19.pdf (981.96 KB) November 5, 2019 November 5, 2019

8. Closure and Reclamation

Final Closure and Reclamation Plan
Document Received/Sent Uploaded
S19L1-003 - Closure and Reclamation Plan - Apr_24_20.pdf (848.79 KB) April 24, 2020 April 24, 2020