GNWT-INF - W2025X0003
Status:
Closed
Authorization:
Land Use Permit
Activity:
Miscellaneous
Start:
Expiry:
Staff:
Roberta Judas
to replace the Dehk’è Frank Channel Bridge (Project) on the Highway-3 corridor. Project Activities include:
- construction and operation of a temporary camp and a laydown area;
- re-alignment of the Right-of-Way
- replacement of the existing bridge
- installation of temporary drainage system and construction of permanent drainage system with new culverts
- construction of temporary ice bridges
- rock blasting to construct temporary accesses to build new bridge and deconstruct the other.
Displaying 1 - 3 of 3
6. Management Plans
Document | Received/Sent | Uploaded |
---|---|---|
Dehk’è Frank Channel Bridge - LUP Application - Engagement Plan - May 5_25.pdf (19.97 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
Dehk’è Frank Channel Bridge - LUP Application - Spill Contingency Plan - May 5_25.pdf (12.8 MB) |
Document | Received/Sent | Uploaded |
---|---|---|
Dehk’è Frank Channel Bridge - LUP Application - Waste Management Plan - May 5_25.pdf (11.55 MB) |