Arctic Canadian Diamond Company Ltd. - W2016F0006
- All maps from Natural Resources Canada
200 km
Status:
Closed
Authorization:
Land Use Permit
Activity:
Road Private
Start:
July 19, 2016
Expiry:
July 18, 2023
Staff:
Rhiana Bams
(This Permit was previously permitted under Permits W2008F0009 and MV2001F0032)
This Permit entitles Arctic Canadian Diamond Company Ltd. to conduct the following land-use operation:The construction, operation, and maintenance of a haul road to the Pigeon and Sable Pit developments, including the construction of water crossings, caribou crossings, and the development of a spur road to access and set up facilities at Falcon Lake for the purpose of road watering.
The Project is for Mining and Associated Activities at the Ekati Mine at 110°36’39”W – 110°36’48”W, 64°44’39”N – 64°44’39”N.
Board approved closure of this file on October 13, 2023.
This Permit entitles Arctic Canadian Diamond Company Ltd. to conduct the following land-use operation:The construction, operation, and maintenance of a haul road to the Pigeon and Sable Pit developments, including the construction of water crossings, caribou crossings, and the development of a spur road to access and set up facilities at Falcon Lake for the purpose of road watering.
The Project is for Mining and Associated Activities at the Ekati Mine at 110°36’39”W – 110°36’48”W, 64°44’39”N – 64°44’39”N.
Board approved closure of this file on October 13, 2023.
Displaying 1 - 4 of 4
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
W2016F0006 - Ekati - Sable Road Safety Modification - Jun 23_22.pdf (206.24 KB) | ||
W2016F0006 - Ekati - Pigeon and Sable Haul Road - Spill Report - 2021104 - Apr 19_21.pdf (170.67 KB) | ||
W2016F0006 - Ekati - Dominion Letter Re Temporary Suspension - Update 1 - Mar 27_20.pdf (1.37 MB) | ||
W2016F0006 - Ekati - Pigeon and Sable Haul Road - Spill Report - 2019275 - Aug 13_19.pdf (168.9 KB) |