GNWT-INF (Sahtu) - S24E-006
Status:
Issued
Authorization:
Land Use Permit
Activity:
Road Public
Start:
September 7, 2024
Expiry:
September 6, 2029
Staff:
Fatima Youssef
The Project includes the relocation of the Oscar Creek Bridge located at KM1054.4 of the Mackenzie Valley Winter Road (MVWR) to a location 2.9 kilometers (km) to the east (upstream), and re-alignment of the MVWR from approximately KM1051 to KM1056 to connect with the new bridge location |