Enbridge Pipelines (NW) Inc. - S17L1-004
Status:
Expired
Authorization:
Licence
Activity:
Industrial
Start:
February 7, 2018
Expiry:
February 6, 2020
Staff:
Bonnie Bergsma
Enbridge Pipelines (NW) Inc. is proposing to conduct Line 21 pipeline maintenance digs within the Saline River (KP 180.168 and KP 180.280). All excavation activities will be contained within Enbridge's existing right-of-way (MV2013P0011) however the Project will involve a watercourse crossing and there is the potential for a channel diversion.
Additional off-right-of-way land is required for temporary work space to accommodate vehicle and equipment staging, temporary material storage and excavation isolation activities. The associated application for a Type A Land Use Permit is S17P-005.
Additional off-right-of-way land is required for temporary work space to accommodate vehicle and equipment staging, temporary material storage and excavation isolation activities. The associated application for a Type A Land Use Permit is S17P-005.
Displaying 1 - 5 of 5
1. Permit - Licence - Other Issuances
Document | Received/Sent | Uploaded |
---|---|---|
S17L1-004 - Enbridge Pipelines Inc. - Issuance Letter_Feb.7_18.pdf (335.37 KB) | ||
S17L1-004 - Enbridge Pipelines Inc. - Reasons for Decision_Feb.7_18.pdf (397.63 KB) | ||
S17L1-004 - Enbridge Pipelines Inc. - Water Licence_Feb.7_18.pdf (473.57 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
S17L1-004 - Enbridge - Security Receipt Confirmation - Feb 26_18.pdf (694.16 KB) | ||
S17L1-004 - Enbridge - Receipt - Water Use Fees - Feb 13_18.pdf (45.46 KB) |