GNWT-INF - MV2023X0029
Status:
Issued
Authorization:
Land Use Permit
Activity:
Miscellaneous
Start:
December 15, 2023
Expiry:
December 14, 2028
Staff:
Tyree Mullaney
For the construction of a transmission line to connect Dory Point and the communities of Fort Providence and Kakisa to the Taltso Hydroelectric system at an interconnnection point near Hay River.
Displaying 1 - 17 of 17
2. Initial/Renewal Application
Document | Received/Sent | Uploaded |
---|---|---|
GNWT-INF - Transmission Line - New Type A Land Use Permit - Review Comments and Responses - Dec1_23.pdf (308.99 KB) | ||
GNWT-INF - Transmission Line - Deadline Extension Request - Responses - Nov1_23.pdf (197.99 KB) | ||
GNWT-INF - Transmission Line - Request for Extension to Comments - Oct27_23.pdf (185.67 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
GNWT-INF - Transmission Line - Notice of Timeline Pause - Nov24_23.pdf (196.01 KB) |
Document | Received/Sent | Uploaded |
---|---|---|
GNWT-INF - Transmission Line - Notification - Preliminary Screening Determination - Dec1_23.pdf (461.59 KB) |