Skip to main content

GNWT-INF - MV2023L8-0012

​The Department of Infrastructure (INF) is planning to replace two existing culverts at km 139.8 (dia. 800 mm) and km 140.3 (dia. 1000 mm), install a new culvert at km 140.7 (dia. 800 mm) and place fill into the water between km 139.4 -141 to bring road grade to design height. The land use activities will fall under the Highway 3 Land Use Permit MV2017X0008 (Hwy 3 Km 124-338.8). 


Documents

Uploaded On or After
Uploaded On or Before
Displaying 1 - 2 of 2
5. Reports and Studies
Annual Reports
Document Received/Sent Uploaded
GNWT-INF - 2024 Annual Report - Mar28_25.pdf (414.02 KB)
Operations and Notifications
Document Received/Sent Uploaded
GNWT-INF - Highway 3 Rehabilitation - Date of commencement of project activities - Aug1_24.pdf (262.18 KB)