Skip to main content

Strategic Oil and Gas Ltd. - MV2022X0018

​Cameron Hills Field and well M-31 abandonment, remediation, and reclamation. Program implementation is planned for five years beginning in 2022. The Program includes forty-four wells and associated infrastructure, camps, pipelines, sumps, bridges, access roads, creek crossings, granular sources (gravel pit, clay borrow pits, and peat pit), and Battery Site

Documents

Uploaded On or After
Uploaded On or Before
Displaying 1 - 53 of 53
2. Initial/Renewal Application
Application and Related Docs
Document Received/Sent Uploaded
Strategic – Issuance - Review Comment Table - Dec22_22.pdf (993.94 KB)
Strategic - Att 7 EA03-005 Developers Assessment Report - Nov4_22.pdf (4.27 MB)
Strategic - Att 7 - Well site Phase I ESA - M-74.pdf (3.61 MB)
Strategic - Updated Permit Application Form - Nov4_22.pdf (609.42 KB)
Strategic - Att 3 - Production Licences - Nov4_22.pdf (17.73 MB)
Strategic - Att 5 - Waste Management Plan - Updated - Nov1_22.pdf (6 MB)
Strategic - Att 6 - Engagement Plan v.2 - Nov4_22.pdf (425.89 KB)
Strategic - Att 7 - Well site Phase I ESA - B-38 - Nov4_22.pdf (6.34 MB)
Strategic - Att 7 - Well site Phase I ESA - C-50 - Nov4_22.pdf (8.71 MB)
Strategic - Att 7 - Well site Phase I ESA - F-73 - Nov4_22.pdf (13.09 MB)
Strategic - Att 7 - Well site Phase I ESA - F-75 - Nov4_22.pdf (10.4 MB)
Strategic - Att 7 - Well site Phase I ESA - F-77 - Nov4_22.pdf (7.7 MB)
Strategic - Att 7 - Well site Phase I ESA - G-21 - Nov4_22.pdf (7.6 MB)
Strategic - Att 7 - Well site Phase I ESA - I-10 - Nov4_22.pdf (26.95 MB)
Strategic - Att 7 - Well site Phase I ESA - I-74 - Nov4_22.pdf (9.05 MB)
Strategic - Att 7 - Well site Phase I ESA - J-04 - Nov4_22.pdf (15.61 MB)
Strategic - Att 7 - Well site Phase I ESA - J-37 - Nov4_22.pdf (8.35 MB)
Strategic - Att 7 - Well site Phase I ESA - L-44 - Nov4_22.pdf (10.73 MB)
Strategic - Att 7 - Well site Phase I ESA - M-31 - Nov4_22.pdf (10.05 MB)
Strategic - Att 7 - Well site Phase I ESA - M-49 - Nov4_22.pdf (6.4 MB)
Strategic - Att 7 - Well site Phase I ESA - N-06 - Nov4_22.pdf (5.14 MB)
Strategic - Land Use Permit Application - DRAFT Conditions - Nov 10_22.pdf (511.71 KB)
Strategic - Updated Cover Letter - Nov4_22.pdf (584 KB)
Strategic - Att 4 - Main Camp and Potential Layout - Nov1_22.pdf (628.31 KB)
Strategic - Att 6 - Engagement Log - Nov4_22.pdf (175.59 KB)
Strategic - Att 6 - NWTMN Notification Letter - Nov4_22.pdf (118.3 KB)
Strategic - Att 7 - Well site Phase I ESA - 2B-09 - Nov 4_22.pdf (8.14 MB)
Strategic - Att 7 - Well site Phase I ESA - 2F-73 - Nov4_22.pdf (8.24 MB)
Strategic - Att 7 - Well site Phase I ESA - A-68 - Nov4_22.pdf (5.81 MB)
Strategic - Att 7 - Well site Phase I ESA - A-73 - Nov4_22.pdf (8.84 MB)
Strategic - Att 7 - Well site Phase I ESA - B-25 - Nov4_22.pdf (6.94 MB)
Strategic - Att 7 - Well site Phase I ESA - C-16 - Nov4_22.pdf (6.27 MB)
Strategic - Att 7 - Well site Phase I ESA - E-07 - Nov4_22.pdf (6.06 MB)
Strategic - Att 7 - Well site Phase I ESA - L-29 - Nov4_22.pdf (8.31 MB)
Strategic - Att 7 - Well site Phase I ESA - N-28 - Nov4_22.pdf (13.22 MB)
Strategic - Receipt - Application Fee - Nov4_22.pdf (63.03 KB)
Strategic - Land Use Permit Application - Incomplete - Oct 20_22.pdf (226.55 KB)
Strategic - Appendix 1 Environmental Protection Plan - Oct11_22.pdf (1.25 MB)
Strategic - Appendix 1-D Table 1 Well-Specific SOW - Oct11_22.pdf (158.3 KB)
Strategic - Appendix 1-F Guidelines for Developers - Oct11_22.pdf (40.84 KB)
Strategic - Appendix 5 - Emergency Response Plan - Oct11_22.pdf (8.4 MB)
Strategic - Appendix 7 - Wildlife Safety - Oct11_22.pdf (3.61 MB)
Strategic - Appendix 8 - Receivership Order and SDLs - Oct11_22.pdf (9.14 MB)
Strategic - Appendix 10 - Site Wide Monitoring Program - Oct11_22.pdf (8.14 MB)
Strategic - Land Use Permit Application - Oct11_22.pdf (1016.79 KB)
Strategic - Appendix 1-A - OROGO Compliance Notification - Oct11_22.pdf (553.49 KB)
Strategic - Appendix 1-B Combined Site Photos - Oct11_22.pdf (17.81 MB)
Strategic - Appendix 1-C Environmental Inspection Reports - GNWT-Lands - Oct11_22.pdf (19.92 MB)
Strategic - Appendix 1-E - Engagement Package - Oct11_22.pdf (3.4 MB)
Strategic - Appendix 2 - Program Area Maps and Figures - Oct11_22.pdf (5.62 MB)
Strategic - Appendix 3 - Survey Plans - Oct11_22.pdf (10.18 MB)
Strategic - Appendix 4 - Anticipated equipment List - Oct11_22.pdf (89.5 KB)
Strategic - Appendix 9 - Conceptual Closure and Reclamation Plan V5 - Oct11_22.pdf (27.5 MB)