Northwest Territories Power Corporation - MV2020X0004
Status:
Issued
Authorization:
Land Use Permit
Activity:
Miscellaneous
Start:
July 2, 2020
Expiry:
July 1, 2025
Staff:
Andrew Wheeler
Construction of replacement support facilities and decommissioning of existing facilities as part of theTaltson Hydroelectris Facility overhaul.
Displaying 1 - 7 of 7
5. Reports and Studies
Document | Received/Sent | Uploaded |
---|---|---|
NTPC - Taltson - Inspectorion Report - Sept 9, 2024 - Nov22_24.pdf (10.72 MB) | ||
NTPC - Taltson - Inspection Report - February 20, 2024 - Mar 2_24.pdf (4.99 MB) | ||
NTPC - Taltson - Inspection Report - July 13, 2023 - Aug8_23.pdf (5.97 MB) | ||
NTPC - Taltson - Inspection Report - May 26, 2022 - Jun8_22.pdf (3.98 MB) | ||
NTPC - Taltson - Inspection Report - July 2021 - Aug16_21.pdf (11.62 MB) | ||
NTPC - Taltson Facility Upgrades - Inspection Report - July 2021 - Aug13_21.pdf (11.62 MB) | ||
NTPC - Taltson Upgrades - Notification of Inspection - Email Correspondence - Aug6_21.pdf (160.85 KB) |