Enbridge Pipelines (NW) Inc. is proposing to conduct Line 21 pipeline maintenance digs within the Saline River (KP 180.168 and KP 180.280).  All excavation activities will be contained within Enbridge's existing right-of-way (MV2013P0011) however the Project will involve a watercourse crossing and there is the potential for a channel diversion. 
Additional off-right-of-way land is required for temporary work space to accommodate vehicle and equipment staging, temporary material storage and excavation isolation activities.  The associated application for a Type A Land Use Permit is S17P-005.


Documents

Displaying 1 - 41 of 41
E.g., 06/20/2019
E.g., 06/20/2019

1. Permit - Licence - Other Issuances

All Issuances
Document Received/Sent Uploaded
S17L1-004 - Enbridge Pipelines Inc. - Water Licence_Feb.7_18.pdf (473.57 KB) February 7, 2018 February 8, 2018
S17L1-004 - Enbridge Pipelines Inc. - Issuance Letter_Feb.7_18.pdf (335.37 KB) February 7, 2018 February 8, 2018
S17L1-004 - Enbridge Pipelines Inc. - Reasons for Decision_Feb.7_18.pdf (397.63 KB) February 7, 2018 February 8, 2018
Security and Water Use Fees
Document Received/Sent Uploaded
S17L1-004 - Enbridge - Security Receipt Confirmation - Feb 26_18.pdf (694.16 KB) February 26, 2018 February 26, 2018
S17L1-004 - Enbridge - Receipt - Water Use Fees - Feb 13_18.pdf (45.46 KB) February 13, 2018 February 14, 2018

2. Initial/Renewal Application

Application and Related Docs
Document Received/Sent Uploaded
S17L1-004 - WL Application Fee - Feb 13_18.pdf (51.16 KB) February 13, 2018 February 19, 2018
S17L1-004 - Enbridge - Receipt - Water Licence Application Fee - Feb 13_18.pdf (51.16 KB) February 13, 2018 February 14, 2018
S17L1-004 - Enbridge - Draft Water Licence - Jan 11_17.pdf (578.53 KB) January 11, 2018 January 11, 2018
S17L1-005 S17P-005 - Enbridge - Line 21 - KP 180.168 and KP 180.28 - NEB Notification - Dec 20_17.pdf (774.37 KB) December 20, 2017 January 9, 2018
S17L1-004 S17P-005 - Enbridge - New WL and LUP - Deemed complete - Dec 18_17.pdf (320.26 KB) December 18, 2017 December 18, 2017
S17L1-004 S17P-005 - Concordance table - revised WL and LUP application - Dec 14_17.pdf (86.2 KB) December 14, 2017 December 15, 2017
S17L1-004 S17P-005 - Revised New WL application - Dec 14_17.pdf (973.93 KB) December 14, 2017 December 15, 2017
S17L1-004 S17P-005 - Enbridge - Applications Deemed Incomplete - Dec 1_17.pdf (36.71 KB) December 1, 2017 December 1, 2017
S17L1-004 - Enbridge - Line 21 Maintenance - New Water Licence Application - Nov 23_17.pdf (428.99 KB) November 23, 2017 November 24, 2017
S17L1-004 S17P-005 - Enbridge - Line 21 Maintenance Dig Project - Appendix I - Project Description - Nov 23_17.pdf (1.4 MB) November 23, 2017 November 24, 2017
S17L1-004 S17P-005 - Enbridge - Line 21 Maintenance Dig Project - Appendix II - Site Photographs - Nov 23_17.pdf (1.06 MB) November 23, 2017 November 24, 2017
S17L1-004 S17P-005 - Enbridge - Line 21 Maintenance Project - Appendix III - Waste Management Plan Version 1.0 - Nov 23_17.pdf (1.72 MB) November 23, 2017 November 24, 2017
S17L1-004 S17P-005 - Enbridge - Line 21 Maintenance Project - Appendix IV - Spill Contingency Plan Version 1.0 - Nov 23_17.pdf (2.28 MB) November 23, 2017 November 24, 2017
S17L1-004 S17P-005 - Enbridge - Line 21 Maintenance Project - Appendix V - Project Diagram - Nov 23_17.pdf (633.08 KB) November 23, 2017 November 24, 2017
S17L1-004 S17P-005 - Enbridge - LIne 21 Maintenance Project - Appendix VI - Engagement Letters - Nov 23_17.pdf (1.17 MB) November 23, 2017 November 24, 2017
Consultations - Reviews - Work Plans
Document Received/Sent Uploaded
S17L1-004 S17P-005 - Enbridge - Staff Report 1 - Feb 7_18.pdf (815.92 KB) February 7, 2018 February 7, 2018
S17L1-004 S17P-005 - Enbridge - Line 21 Integrity Dig Saline River - Review Summary Table with Attachments - Jan 27_18.pdf (1.35 MB) January 27, 2018 January 27, 2018
S17L1-004 S17P-005 - Enbridge Responses to Review Comments and Draft Conditions with Attachments - Jan 25_18.pdf (405.45 KB) January 25, 2018 January 25, 2018
Further Study Requested Sec. 22.2.b
Document Received/Sent Uploaded
S17L1-004 S17P-005 - Enbridge - Board Decision WL and LUP Application - Further Study Required - Jan 29_18.pdf (96.56 KB) January 29, 2018 January 30, 2018

5. Reports and Studies

Annual Reports
Document Received/Sent Uploaded
S17P-005 - S17L1-004 - Review Comment Table with Letter from GNWT-ENR - Review of 2018 Annual Reports - May 7 _19.pdf (225.87 KB) May 7, 2019 May 7, 2019
S17L1-004 - Line 21 Annual Water Licence Report - Mar 29_19.pdf (10.13 MB) March 29, 2019 April 1, 2019
Inspection Reports
Document Received/Sent Uploaded
S17L1-004 - GNWT-ENR Inspection Report for Feb 26 2018 - Mar 2_18.pdf (702.75 KB) March 2, 2018 March 2, 2018
Operations and Notifications
Document Received/Sent Uploaded
S17L1-004 - Enbridge - Notification of Diversion - Feb 16_18.pdf (62.32 KB) February 16, 2018 February 16, 2018
Preliminary Screening
Document Received/Sent Uploaded
S17P-005 S17L1-004 - Preliminary Screening - Feb 7_18.pdf (338.01 KB) February 7, 2018 February 7, 2018

6. Management Plans

Assorted Management Plans
Document Received/Sent Uploaded
S17L1-004 S17P-005 - revised WMP and SECP - Staff Conformity Confirmation - Feb 16_18.pdf (334.61 KB) February 16, 2018 February 16, 2018
Engagement Plan
Document Received/Sent Uploaded
S17L1-004 S17P-005 - Enbridge - Engagement plan - Dec 22_17.pdf (162.1 KB) December 22, 2017 December 27, 2017
Sediment and Erosion Control
Document Received/Sent Uploaded
S17L1-004 - Enbridge - Revised Erosion and Sediment Control Plan - Version 1.1 - Feb 15_18.pdf (3.13 MB) February 15, 2018 February 16, 2018
S17L1-004 S17P-005 - Enbridge - Sediment and Erosion Control Plan - Dec 22_17.pdf (3.73 MB) December 22, 2017 December 27, 2017
Spill - Contingency - Emergency Response
Document Received/Sent Uploaded
S17L1-004 S17P-005 - Enbridge - Spill Contingency Plan - Version 1.1 - Feb 16_18.pdf (12.6 MB) February 16, 2018 February 19, 2018
S17L1-004 S17P-005 - Staff Confirmation of Conformity - Spill Contingency Plan - Feb 19_18.pdf (283.9 KB) February 19, 2018 February 19, 2018
Waste Management Plan
Document Received/Sent Uploaded
S17L1-004 S17P-005 - Enbridge - Revised Waste Management Plan - Version 1.1 - Feb 15_18.pdf (3.35 MB) February 15, 2018 February 16, 2018

8. Closure and Reclamation

Final Closure and Reclamation Plan
Document Received/Sent Uploaded
S17L1-004 S17P-005 - Board approval - CRP V1- Mar 26_18.pdf (312.49 KB) March 26, 2018 March 27, 2018
S17L1-004 S17P-005 - Staff Report 2 - CRP V1 - Mar 26_18.pdf (486.94 KB) March 26, 2018 March 26, 2018
S17L1-004 - Enbridge - CRP V1 - Review Summary Table and Attachments - Mar 26_18.pdf (378.97 KB) March 26, 2018 March 26, 2018
S17L1-004 S17P-005 - Enbridge - Closure and Reclamation Plan - Version 1.0 - Feb 28_18.pdf (1.89 MB) February 28, 2018 March 1, 2018
S17L1-004 S17P-005 - Extension of submission deadline for CRP - Feb 22_18.pdf (60.54 KB) February 22, 2018 February 22, 2018